Dendreon IMF

Seal Beach, California

General Contractor: Turner
Contract Value: $4.7M
Year Completed: 2010
Scope: Plumbing, Piping, Process
Services: Fabrication, Installation
Delivery: Lump Sum, Plans & Specs

 

Single-story existing shell and core, mezzanine level, and roof. This is a Immunotherapy Manufacturing Facility.

WHITELINE

Murray Company’s contract consisted of plumbing including PVC waste/vent, high purity waste/vent, domestic hot/cold water, industrial water, natural gas, fuel oil system consisting of 4000 gal above ground storage tank and four emergency generators. Mechanical piping including chilled water, heating hot water, steam. Process piping including deionized water, high purity water for human injection and carbon dioxide piping.  This is a fast track project, with only an eight-month schedule to complete.   

 

Dendreon Chillers 064