Universal City, California
General Contractor: Morley Builders
Contract Value: $1.3M
Year Completed: 2015
Scope of Work: General Engineering, Utilities
Services: Engineering, Detailing, Installation
Delivery: General Contracting
Project Description: Nine levels of above ground open air structure in excess of 1.8M sq. ft. with parking for 3500 cars. Upon completion, this will be one of the largest parking structures in the U.S. Construction has begun with earthworks and utility relocations.
Murray Company: Parking structure, earth work, utility relocation. Its location creates a challenge with little or no lay down area. Material deliveries will require tight coordination with the on-site project team.